FastDrivers is a new organization in the driving lesson service provider industry. The organization requires to be competitive and quick in managing processes. The organization is looking forward to implement a website which will be accessed by the customers. The customer will book their driving lessons through the website. FastDrivers will need to collect the information from the website and store into a secured place. In order to perform the internal operations, these set of information are extremely essential. The organization need to implement a technology that will handle the user management method. The customer cannot book a service without logging in. The system will automatically track the instructor and lesson booking details. At the time when a customer tries to book a driving lesson, the proposed technology will validate all the inputted data and process the booking details.
The information system will provide the following benefit to FastDrivers.
2.Project Scope:
The scopes of the project are as following.
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
Cost |
FastDrivers System Implementation |
105 days |
Thu 5/3/18 |
Wed 9/26/18 |
$9,432.00 |
||
Planning |
16 days |
Thu 5/3/18 |
Thu 5/24/18 |
$1,664.00 |
||
Problem Definition |
2 days |
Thu 5/3/18 |
Fri 5/4/18 |
Project Manager |
$192.00 |
|
Project Charter Development |
4 days |
Mon 5/7/18 |
Thu 5/10/18 |
2 |
Project Manager |
$384.00 |
Project Staff Employment |
2 days |
Fri 5/11/18 |
Mon 5/14/18 |
3 |
Project Manager |
$192.00 |
Selection of SDLC Model or Software Development Life Cycle |
2 days |
Tue 5/15/18 |
Wed 5/16/18 |
4 |
Analyst, Project Manager |
$320.00 |
Project Schedule Development |
3 days |
Thu 5/17/18 |
Mon 5/21/18 |
5 |
Project Manager |
$288.00 |
Project Budgeting |
2 days |
Tue 5/22/18 |
Wed 5/23/18 |
6 |
Project Manager |
$192.00 |
Allocate Resoruces Planning |
1 day |
Thu 5/24/18 |
Thu 5/24/18 |
7 |
Project Manager |
$96.00 |
Planning Phase Complete |
0 days |
Thu 5/24/18 |
Thu 5/24/18 |
8 |
$0.00 |
|
System Analysis and Requirements |
18 days |
Fri 5/25/18 |
Tue 6/19/18 |
$1,440.00 |
||
Identification of Business Requirements |
3 days |
Fri 5/25/18 |
Tue 5/29/18 |
9 |
Analyst |
$192.00 |
Identification of System Requirement |
4 days |
Wed 5/30/18 |
Mon 6/4/18 |
11 |
Analyst |
$256.00 |
Identification of User Requirement |
1 day |
Tue 6/5/18 |
Tue 6/5/18 |
12 |
Analyst |
$64.00 |
Verify Requirements |
3 days |
Wed 6/6/18 |
Fri 6/8/18 |
13 |
Analyst, Project Manager |
$480.00 |
Evaluating Requirement |
3 days |
Mon 6/11/18 |
Wed 6/13/18 |
14 |
Analyst |
$192.00 |
Documentation of Requirement |
4 days |
Thu 6/14/18 |
Tue 6/19/18 |
15 |
Analyst |
$256.00 |
System Analysis Phase Complete |
0 days |
Tue 6/19/18 |
Tue 6/19/18 |
16 |
$0.00 |
|
System Design |
32 days |
Wed 6/20/18 |
Thu 8/2/18 |
$2,456.00 |
||
Architecture Designing of UK Library Online System |
3 days |
Wed 6/20/18 |
Fri 6/22/18 |
17 |
Designer |
$168.00 |
UML Diagrams Designing |
4 days |
Mon 6/25/18 |
Thu 6/28/18 |
19 |
Designer |
$224.00 |
Unit Design |
1 day |
Mon 6/25/18 |
Mon 6/25/18 |
19 |
$0.00 |
|
Database Design |
10 days |
Fri 6/29/18 |
Thu 7/12/18 |
$1,080.00 |
||
Selection of Attributes and Entities |
3 days |
Fri 6/29/18 |
Tue 7/3/18 |
20 |
Database Developer, Designer |
$480.00 |
Schema Diagram Creation |
3 days |
Wed 7/4/18 |
Fri 7/6/18 |
23 |
Designer |
$168.00 |
Generate Entity Relationship Diagram or ERD |
2 days |
Mon 7/9/18 |
Tue 7/10/18 |
24 |
Designer |
$112.00 |
Database Normalizaion |
2 days |
Wed 7/11/18 |
Thu 7/12/18 |
25 |
Database Developer, Designer |
$320.00 |
Webiste Design |
9 days |
Fri 7/13/18 |
Wed 7/25/18 |
$648.00 |
||
User Interaction Designing |
3 days |
Fri 7/13/18 |
Tue 7/17/18 |
26 |
Web Designer |
$192.00 |
User Interface Designing |
3 days |
Wed 7/18/18 |
Fri 7/20/18 |
28 |
Web Designer |
$192.00 |
Functionality Confirmation |
3 days |
Mon 7/23/18 |
Wed 7/25/18 |
29 |
Web Developer |
$264.00 |
Network Diagram Designing |
3 days |
Thu 7/26/18 |
Mon 7/30/18 |
30 |
Designer |
$168.00 |
Network Design |
3 days |
Tue 7/31/18 |
Thu 8/2/18 |
31 |
Designer |
$168.00 |
Completion of Designing Phase |
0 days |
Thu 8/2/18 |
Thu 8/2/18 |
32 |
$0.00 |
|
Development |
38 days |
Fri 8/3/18 |
Tue 9/25/18 |
$3,712.00 |
||
Implement Webiste |
12 days |
Fri 8/3/18 |
Mon 8/20/18 |
33 |
Web Developer |
$1,056.00 |
Implement Unit Application |
18 days |
Tue 8/21/18 |
Thu 9/13/18 |
35 |
Coder |
$1,872.00 |
Implement Database |
5 days |
Fri 9/14/18 |
Thu 9/20/18 |
36 |
Database Developer |
$520.00 |
Implement Network |
3 days |
Fri 9/21/18 |
Tue 9/25/18 |
37 |
Web Developer |
$264.00 |
Complete of Development |
0 days |
Tue 9/25/18 |
Tue 9/25/18 |
38 |
$0.00 |
|
Deployment |
1 day |
Wed 9/26/18 |
Wed 9/26/18 |
$160.00 |
||
Go Live |
1 day |
Wed 9/26/18 |
Wed 9/26/18 |
39 |
Analyst, Project Manager |
$160.00 |
Deployment Completion |
0 days |
Wed 9/26/18 |
Wed 9/26/18 |
41 |
$0.00 |
3.Major Functions of System:
The major functions of the system are as following.
Login: The system will allow the customers to login to the system. The system will collect input from the website and store it into the database.
Registration: For the customers who purchase service for the first time will register into the system and generate user id and password.
Service booking: The customer will book the lessons for a specific day and time. During the booking, the system will check whether the user input date is valid or not.
4.TCO:
5. DFD
6. ERD:
7.Interfaces
Input Section:
Al-Masree, H.K., 2015. Extracting Entity Relationship Diagram (ERD) from relational database schema. International Journal of Database Theory and Application, 8(3), pp.15-26.
Cassidy, A., 2016. A practical guide to information systems strategic planning. CRC press.
Clark, R.C. and Mayer, R.E., 2016. E-learning and the science of instruction: Proven guidelines for consumers and designers of multimedia learning. John Wiley & Sons.
Kadam, K.S. and Onkar, V.C., 2015. A review paper on student information supervision system. International Journal of Research In Science & Engineering, 1, pp.66-72.
Laudon, K.C. and Laudon, J.P., 2016. Management information system. Pearson Education India.
Lee, S.H., Go, K.W., Ahn, G.H., Park, H.S., Han, C.K., Shim, J.B., Kang, G.C. and Lee, H.J., 2017. A Study on Automotive Attack Database and Data Flow Diagram for Concretization of HEAVENS: A Car Security Model. Structure, 2277, p.82477.
Long, J.E., 2018. Relationships between common graphical representations used in system engineering. INSIGHT, 21(1), pp.8-11.
Masci, P., Rukš?nas, R., Oladimeji, P., Cauchi, A., Gimblett, A., Li, Y., Curzon, P. and Thimbleby, H., 2015. The benefits of formalising design guidelines: A case study on the predictability of drug infusion pumps. Innovations in Systems and Software Engineering, 11(2), pp.73-93.
Pearlson, K.E., Saunders, C.S. and Galletta, D.F., 2016. Managing and Using Information Systems, Binder Ready Version: A Strategic Approach. John Wiley & Sons.
Sarkar, D., Jana, T. and Saha, S., 2015. LMPID: A manually curated database of linear motifs mediating protein–protein interactions. Database, 2015.
Wager, K.A., Lee, F.W. and Glaser, J.P., 2017. Health care information systems: a practical approach for health care management. John Wiley & Sons.
Zahabi, M., Kaber, D.B. and Swangnetr, M., 2015. Usability and safety in electronic medical records interface design: a review of recent literature and guideline formulation. Human factors, 57(5), pp.805-834.
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more