DQ #1: You are the project manager assigned to renovate a parking garage. What might be some examples of leads you encounter when scheduling work activities?
Instructions: This question involves the student posting a substantive response of at least 250 words and reference the textbook(s) and at least one (1) scholarly journal article. The journal article should provide substantive support to your answer. In addition, to the initial post of the discussion, the student is required to respond to any TWO (2) classmates’ responses. These responses should be substantive and a minimum of 100 words. A response such as “I agree” or “I liked what was said” is NOT substantive and will not be counted for course credit. Please be aware of time constraints as all initial responses to discussion questions are due by Thursday evening at 11:59 p.m. EST and discussion question responses are due on Sunday evening at 11:59 p.m. EST
Responses:
1) for Sharada
Lead simply describes as the amount of time whereby a successor activity has the capacity to be advanced with respect to activity’s predecessor. Lead is usually helpful in a project which is supposed to be completed within a short period of time because the successor activity is overlapped with its predecessor before it reaches a point of waiting for preceding one to be completed. During renovation of a parking garage there are several leads which the project manager is likely to encounter when scheduling the activities. This paper will briefly explain some of the lead activities which are likely to be encountered by the manager.
While renovating the walls of the same garage whereby the walls are labelled as wall x and wall y. The engineer is interested in delaying the renovation of wall x for approximately six days since the material utilized for the renovation of both the walls is new and the engineer wishes to test wall y first. The time gap between renovations of the two walls of the gaps start dates of the renovation is six days is referred to as lag. Additionally if two different materials are to be utilized in renovation of both walls of the garage, then the project might take a longer period of time. If the material used for renovation of wall x is not available for additional seven days, then wall y which qualifies to be the successor activity for which the material is available will have to be renovated first(Kerzner,2017).
As a result of this, wall y is which is renovated prior to wall x with a lead time of seven days. In the given scenario the best lead activity example is to deal with one wall of the garage and complete it first. In conclusion in project management lead entails the acceleration of the successor activities with the objective of using only on finish-to-start activities relationships.
2) for Venkata pavan
Lead time is the speedup of the successor activity. In different words, the next activity can start (and also can be handled parallelly) when the first activity started. Lead is something which is simply observed activities by finish-to-start connections: A must end before B can begin (Stevenson, 2007).
In order to leverage a lead, which will reduce the entire mixed continuation of both exercises, the dependency need to be optional, meaning that there exists no real restriction on completing A before B starts. Lag remains the delay regarding a successor activity and also describes time that need to reach prior to the next activity can start. There exist no resources linked by a lag.
Lag may be seen in projects by all connection types: finish-to-start, start-to-start, finish-to-finish, and start-to-finish. Lag may be seen in projects by all connection types: finish-to-start, start-to-start, finish-to-finish, and start-to-finish. Lag may be seen in projects by all connection types: finish-to-start, start-to-start, finish-to-finish, and start-to-finish (Kloppenborg, 2019).
Lead Time remains an essential constituent for client satisfaction. Typically, consumers need goods or service as quick as potential with least effort. For construction and assembly, the idea of Lead Time remains linked to and also holds a close connection by the amount of record that survives at various periods in the overall construction. If Client Lead Time remains less than the Material Lead Times, Production Lead Times, or rather a Cumulative Lead Times it will end up in the holding of stock in the supply chain at some or each and every point.
In this scenario of renovating a parking garage, one lead example I can think of is all the material needed for the renovation of parking can be ordered on the first day of the project start itself instead of waiting for the completion of the renovation design, this will ultimately decrease the time of the project.
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more