2. (TCO E) The following information is extracted from a project to develop a state-of-the-art alternative power energy storage device.
Activity Duration Predecessors Resources
A 4 days — 1 research engineer
B 3 days A 1 marketing specialist
C 5 days A 1 design engineer
D 3 days A 1 design engineer
E 3 days B 1 prototype builder
F 2 days D 1 test engineer
The owner has stipulated that in order to provide continuity throughout the project, the same individual must handle all activities under his or her discipline. Activities on this project cannot be split.
(a) Identify any resource conflicts in the above project. State the activities involved, the time frame of the conflict(s), which resources are involved, and the quantity required.
(b) Given the owner’s stipulation regarding project continuity and the need to minimize project duration, how can this conflict be resolved? What will be the effect on the project duration? (Points : 20)
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more